Town Projects
Capital Projects Planned for 2013
Engineering Department
• Street maintenance - overlay ($889,194)
• Street maintenance – crack seal, chip seal and concrete replacement ($250,000)
• Bridge replacement – WCR 21 at Greeley No. 2 Canal, 2013-2014 project ($61,875 + $247,500 grant)
• WCR 13 at Poudre River - repair deck and bridge ($100,000)
• I-25/SH 392 Interchange - construction ($825,000)
• I-25/SH 392 Interchange - enhancements ($250,000)
• Eagle Crossing Subdivision – infrastructure development ($642,342)
• Eastman Park / Cornerstone Roundabout - design ($63,000)
• WCR 23 and SH392 – Intersection improvements ($150,000)
• WCR 17 – safety guard rails ($160,000)
• Waste Water Treatment Plant – Headworks and lift station ($252,000) balance of EDA grant work
• Storm Drainage - Law Basin Master Plan Channel ($265,360 + $590,640 FEMA grant)
Parks, Recreation & Culture Department
• Eastman Park – multipurpose court ($60,000)
• Chimney Park – shade over concession area ($60,000)
• Main Park – retrofit east playground to ADA standards ($112,937)
• Neighborhood Park Development – Northern Lights Park ($982,431)
• Stonehenge Neighborhood Park - Reimbursement ($30,000)
• Windsor Village Park – irrigation site reconstruction ($120,000)
• Poudre Trail - extension from Westwood Village ($250,000); extension in Three Bells I conservation easement share with Larimer County ($25,000)
• Windsor Trail – trail parallel to South 7th Street ($200,000); trail connection at Windsor Highlands and Poudre Valley REA ($113,000); design railroad underpass at Grasslands ($24,000); BROE easement acquisition ($5,000)
• Town of Windsor Museum - Interpretive Landscape Plan ($50,000)
• Cemetery Master Plan - revisions, including irrigation design and entry gates ($150,000)
• ADA Title II Compliance – various projects ($214,941)
• Non-Potable Water – redrill Boardwalk Park well; engineer pipe encasement through Universal Forest Products ($56,700); water acquisition ($200,000)
• Windsor Lake – Chimney Park flow control, Chestnut flow measurement station, & Stormwater flow control at splitter box ($124,000)
Public Works Department
• Railroad Crossing improvements - 7th Street ($24,000)
• Sewer System Rehab - Replace Force Main to Gravity Sewer ($165,000)
• Three million gallon water tank - ($1,400,000 + $800,000 DOLA grant pending)
• Water line - replacement on 4th Street ($150,000)
• Sewer Line - Rehab ($77,000)
• Sewer – Replace Lift Station #4 pumps and generator ($200,000)
• Manhole - Rehab ($32,000)
• Vehicles, Fleet - New, Replacement, Lease Exchange ($483,500)
Where Do I Find Available Bids?
Find available bids in the the Bids and RFP's page listed in the left menu of the home page or under Services on the main menu.
Notify Me of New Bid Postings
You may also subscribe to be notified of new bid postings, as well as through the Bids and RFP page.